Specific Process Knowledge/Etch/IBE⁄IBSD Ionfab 300/IBE magnetic stack etch: Difference between revisions
Line 45: | Line 45: | ||
[[image:IBE magnetic stack A19-13.jpg|300x300px|thumb|center|Magnetic stack of Ta/MnIr/NiFe/Ta/Tao/Ta/MnIr/NiFe/Ta. Redeposition of etched material at photo resist. Profile ~78°]] | [[image:IBE magnetic stack A19-13.jpg|300x300px|thumb|center|Magnetic stack of Ta/MnIr/NiFe/Ta/Tao/Ta/MnIr/NiFe/Ta. Redeposition of etched material at photo resist. Profile ~78°]] | ||
! | ! | ||
[[image:IBE magnetic stack A16-13.jpg|300x300px|thumb|center|]] | [[image:IBE magnetic stack A16-13.jpg|300x300px|thumb|center|Etched magnetic stack with pool structure transfer. Chosen etch parameters result in severe footing]] | ||
! | ! | ||
[[image:IBE magnetic stack A3-13.jpg|300x300px|thumb|center|]] | [[image:IBE magnetic stack A3-13.jpg|300x300px|thumb|center|Etched magnetic stack with pool structure transfer. Chosen etch parameters result in severe trenching]] | ||
|} | |} |
Revision as of 14:07, 27 September 2012
End point detection is achieved by SIMS, and the etch rate is approximately 25 Nm/min. Resist stripping can be hard due to burned resist, to remedy this try to lover the current; this will though chance the sidewall angle. For help, discussion and further info please contact Kristian Hagsted Rasmussen.
Results from the acceptance test in February 2011
Process parameters for the acceptance test
Parameter | Ti etch acceptance |
---|---|
Neutalizer current [mA] | 450 |
RF Power [W] | 800 |
Beam current [mA] | 400 |
Beam voltage [V] | 500 |
Beam accelerator voltage | 500 |
Ar flow to neutralizer [sccm] | 5.0 |
Ar flow to beam [sccm] | 10.0 |
Rotation speed [rpm] | 20 |
Stage angle [degrees] | 5 |
Helium backside cooling [Torr] | 37.5 |